Robot Lead Times: What Actually Takes the Time
A stock arm ships in 15–20 days. An engineered cell takes 45–90. Here is where the weeks go, by product family, using the lead times published on our own product pages.
Stock Builds: 7–20 Days
Arms we build in batches — the CS series, TR-R series, TR10/TR20/TR30 cobots, most SCARA and 6-axis welding arms — leave in one to three weeks. The clock starts when the purchase order and the technical confirmation are both signed; the technical confirmation is where most delays happen, because the tooling drawing has to be approved before the arm is configured.
Configured Machines: 20–45 Days
Palletizing arms with a gripper, AMRs with a top module, welding cells with a positioner: the robot is standard, the interface is not. A 165 kg palletizing arm is 20 days as an arm and about 35–45 days as a working cell with gripper, safety and pattern software.
Engineered Lines: 45–90 Days
Conveyors, filling and packing lines, glove or mask production lines, CTU warehouses: 60–90 days is normal because the line is built to order and tested as a line. A 300 kg CTU is quoted at 35–45 days; a full automated warehouse with several dozen units is a project schedule, not a product lead time.
The Part Nobody Counts: Freight
Sea freight from Shenzhen to Rotterdam or Hamburg is typically 25–35 days door to door plus customs; to Jebel Ali about 20; to Los Angeles 18–25. Air freight is 5–7 days and costs several times more — worth it for a spare part that stops a line, rarely for a machine. If a project has a hard date, work backwards from the installation week, not from the order date.
Questions We Get Asked
Can lead time be shortened?
For stock builds, sometimes — ask for units already in production. For engineered lines the honest answer is no: compressing assembly is how machines arrive with faults.
Does the lead time include shipping?
No. Product pages quote ex-works build time; freight and customs are quoted separately per destination port.
What do I need to provide to start the clock?
Purchase order, technical confirmation, and for cells the approved tooling and layout drawing. Payment terms are agreed at quotation.
Machines This Applies To
- 165 kg Palletizing Robot, 3,000 mm ReachTR10165B-310 · 20 days
- 300 kg CTU Mobile Robot for Rack HandlingTR-CTU300 · 35–45 days
- ROKAE CR12 Collaborative Robot - 12kg 6-Axis Cobot for Heavy-Duty TasksCR12 · 15–30 days
Ask an engineer about your case
Keep Reading
- What documents ship with a machine (and what to ask for before you sign)Manual, drawings, I/O list, spare-parts list, FAT report, packing list. Missing one of these turns commissioning into a month of emails.
- Glass facade cleaning robots: what a building actually has to provideThe robot is the small part of the decision. Anchors, water, roof access, wind limits and the contract with the cleaning crew decide whether it ever gets used.
- Exoskeleton selection: passive or powered, and which body part actually hurtsPassive units borrow energy from posture; powered units add torque. The right choice depends on the task duration, the load, and whether the worker walks or stands.