Robot Lead Times: What Actually Takes the Time

A stock arm ships in 15–20 days. An engineered cell takes 45–90. Here is where the weeks go, by product family, using the lead times published on our own product pages.

Stock Builds: 7–20 Days

Arms we build in batches — the CS series, TR-R series, TR10/TR20/TR30 cobots, most SCARA and 6-axis welding arms — leave in one to three weeks. The clock starts when the purchase order and the technical confirmation are both signed; the technical confirmation is where most delays happen, because the tooling drawing has to be approved before the arm is configured.

Configured Machines: 20–45 Days

Palletizing arms with a gripper, AMRs with a top module, welding cells with a positioner: the robot is standard, the interface is not. A 165 kg palletizing arm is 20 days as an arm and about 35–45 days as a working cell with gripper, safety and pattern software.

Engineered Lines: 45–90 Days

Conveyors, filling and packing lines, glove or mask production lines, CTU warehouses: 60–90 days is normal because the line is built to order and tested as a line. A 300 kg CTU is quoted at 35–45 days; a full automated warehouse with several dozen units is a project schedule, not a product lead time.

The Part Nobody Counts: Freight

Sea freight from Shenzhen to Rotterdam or Hamburg is typically 25–35 days door to door plus customs; to Jebel Ali about 20; to Los Angeles 18–25. Air freight is 5–7 days and costs several times more — worth it for a spare part that stops a line, rarely for a machine. If a project has a hard date, work backwards from the installation week, not from the order date.

Questions We Get Asked

Can lead time be shortened?

For stock builds, sometimes — ask for units already in production. For engineered lines the honest answer is no: compressing assembly is how machines arrive with faults.

Does the lead time include shipping?

No. Product pages quote ex-works build time; freight and customs are quoted separately per destination port.

What do I need to provide to start the clock?

Purchase order, technical confirmation, and for cells the approved tooling and layout drawing. Payment terms are agreed at quotation.

Machines This Applies To

Ask an engineer about your case

Keep Reading

TROY AssistantSales engineer · replies in seconds
Hi — I’m TROY’s sales engineer bot.
Tell me what you need to automate: part weight, reach or cycle time is enough. I answer in your language and can put you in front of a human engineer in 48 h.
No prices published — quotation per configuration within 48 h · quote form